Port Kembla Coal Terminal Long Travel Drive Upgrade

Commencement

2014

Completion

2014

Type of Contract

Manufacture

Contract Value

AUD <5 million (Manufacture)

Capability Groups

Manufacture

Overview

Globetech Construction was engaged by Port Kembla Coal Terminal to manufacture the upgrade for the long travel drive system.

Scope

Globetech Construction was engaged by Port Kembla Coal Terminal to manufacture the Long Travel Drive suite. The project scope included the design of the drive and safety systems, panel design and manufacture, installation of machinery and electrical panels, field cabling, racking, and commissioning.