Lucas Heights JPG Engineering Leachate Treatment Plant

Commencement

2018

Completion

2019

Type of Contract

Design, Manufacture & Construct

Contract Value

AUD <5 Million (Electrical D&C)

Capability Groups

Manufacturing & Construction

Overview

Globetech and Globetech Construction were engaged by JPG to design, manufacture, and install/commission the expansion of their treatment facility.

Scope

Working closely with JPG Engineering, Globetech and Globetech Construction determined the requirements for the new power infrastructure to support the facility expansion. Once established, Globetech was responsible for the design of the electrical infrastructure, control system upgrades, and the design and manufacture of MCC and control panels, drive systems, as well as associated construction and commissioning activities.

Project Challenges

Key challenges included defining functionality requirements for all potential operating scenarios and integrating new systems into the existing plant. The project also faced difficulties working with limited and potentially inaccurate existing drawings and validating installation content.

How We Managed This

Functionality requirements were finalised through a series of client engagement workshops. Design challenges were addressed by validating the existing installation against current drawings, which then formed the basis for the new design.
Globetech and Globetech Construction leveraged its in-house design, manufacturing, and construction expertise to deliver the project entirely under one roof, providing a single interface to the client.

Value Adding

The project was delivered on schedule and successfully placed into service after commissioning. Globetech and Globetech Construction’s integrated approach ensured seamless coordination, reduced risk, and a high-quality, fully operational expansion for the client.

Zero Harm

The project safety record was excellent with no LTI or MTI’s recorded.

Download the Project Data Sheet

arrow-up-right-banner

Design, Manufacture & Construct

Lucas Heights

Explore Our Other Projects

PS008 – Port Kembla Coal terminal- No 1& 2 Shiploader Upgrades

PS012 – JPG Engineering – Terry Hills – Kimibriki Leachate Treatment Plant

PS013 – Morgan Cement – Port Kembla – Silo Expansion Project