Port Kembla Coal terminal- No 1& 2 Shiploader Upgrades

Commencement

2013

Completion

2014

Type of Contract

Construct

Contract Value

AUD <5 million (Manufacture)

Capability Groups

Construction

Overview

Globetech Construction was engaged by BHPB to refurbish the existing plough control system for the facility.

Scope

Globetech Construction provided full construction services for the project. The scope included refurbishing existing equipment and installing new equipment on ship loaders, supplying and installing new power supplies to the assets, limited supply and installation of new communication network equipment, supply and installation of electrical panels, field cabling, racking, and providing commissioning assistance to ensure compliance with the Quality Management System.

Project Challenges

The project faced several challenges, including the variable condition of the equipment requiring refurbishment and environmental issues on site. Exposure to dust, saltwater mist, and general weather conditions created difficulties, as the location is exposed from all directions.

How We Managed This

Environmental challenges were managed through careful planning and site preparation. Pre-start meetings were used to discuss potential exposure issues, and where possible, barricades and temporary covers were installed to mitigate the effects. Open electrical equipment was closed promptly after work was completed to minimise exposure to salt mist and other elements.

Value Adding

Globetech Construction leveraged its manufacturing expertise to assist with refurbishment work, ensuring the right skills were available to execute the project efficiently. By utilising workshop manufacturing practices and specialised tooling, the team delivered high-quality outcomes while maintaining safety and operational standards.

Zero Harm

The project safety record was excellent with no LTI or MTI’s recorded.

Download the Project Data Sheet

ConstructionEngineering

Port Kembla Coal Terminal

Explore Our Other Projects

PS004 – BlueScope SteelPort Kembla Lime Kiln Drive Upgrade

PS007 – Port Kembla Coal Terminal Long Travel Drive Upgrade

PS006 – Port Kembla CP03 Drawing Machine Upgrade